Injection Problem
A large tier 1 iron ore miner was in the initial stages of quantifying the injection capacity of an aquifer at an iron ore project in the Pilbara. Aquifer injection would be required when the mine is operational due to the need to dispose of hypersaline water produced from dewatering of the pit.
An injection area had been identified and several bores had been drilled but it was not clear what the injection capacity of the aquifer would be based on limited test pumping capability. The main driver of limited test pumping data was due to the hypersaline nature of the water and the limitations this caused on disposal into the environment. Pumping tests lasting more than one day was not viable.
A more detailed injection test regime would be required to quantify the injection capacity of the aquifer. A further complication was that the limited number of bores that had been drilled did not allow the removal of water from one bore and injection to another, this was also not permitted due to licensing requirements. Therefore, the injection test would need to remove water from the same bore it would be injecting into.

Project Engineering Solution
Comprehensive injection testing would require an end-to-end solution, where water would be removed from the bore, stored in a temporary location and then reinjected into that same bore. it was also a necessity that all equipment would have to be removable, with minimal site and environmental impact.
Project Engineering was able to provide a complete service including, water abstraction using Pentium Test Pumping’s (PTP) specialised equipment. Two temporary steel line tanks, with a total capacity of 2.8 ML, and a mobile aquifer injection testing unit provided by Project Engineering WA, using their patented down hole valve.
Using the PTP pump truck and test pumping setup provided several advantages, including the ability to remove water from the bore at rates up to 80 L/s, being able to provide additional test pumping data from the bore due to the ability to safely store water, and the temporary nature of the pump install allowed for quick removal once the tanks were full.
The steel lined tanks required minimal site works, consisting of a compacted pad, with erection and demolition requiring five days in total. Both tanks were joined, which provided sufficient water storage space to ensure all the required injection testing could be performed.
The injection unit provided by Project Engineering was completely mobile allowing for easy installation and removal once the tests were completed. The system operates utilising the proprietary control system with data logging capabilities, providing real time data to ensure the success of the injection trial. The downhole valve ensured that the required flowrate would be maintained regardless of any upstream pumping fluctuations.
Two rounds of injection testing were required, namely, a step-rate test and a constant rate test. The mobility of the equipment used allowed for a reduced timeline whilst maximising testing time. The overall project was delivered within 19 days, including mob and demob of equipment.

Injection Testing Outcomes
Aquifer injection testing was successful with both step rate testing and constant rate testing providing positive results. Together with the pump testing that was completed during the extraction of the water from the bore, invaluable data was obtained for the client.
All work was completed on schedule, within budget and with no safety incidents. Minimal water was discharged into any sumps and the pad was cleared of all equipment.
This project demonstrates an integrated solution for injection testing, where water sources are scarce. It is perfect for initial injection testing, with relatively low costs to provide an initial characterisation of injection performance of an aquifer.